Project Status

Current Status:

  • Recently the contractor has been cutting soil cement in the Southern Blvd. and the 'black' you see on the roadway is a tack coat, prior to interlayer and asphalt placement. This signals a big step forward in the roadway construction.
  • Bridge construction is nearing completion of the critical structural elements (bridge deck), and completed a part of the approach slab installation.

Whats next?:

  • In the coming week (or two) the contractor should install the interlayer and then the asphalt paving to shift traffic and begin work on the northern boulevard along existing Cook Road.
  • As the bridge gets completed (structurally), we will expect to see the contractor begin using it, and possibly removing the 'low-water crossing' seen within Gray's Creek.

November 2024

vimeo-video-thumbnail

October 2024

vimeo-video-thumbnail

September 2024

vimeo-video-thumbnail

August 2024

vimeo-video-thumbnail

July 2024

vimeo-video-thumbnail

June 2024

vimeo-video-thumbnail

May 2024

vimeo-video-thumbnail

April 2024

vimeo-video-thumbnail

March 2024

vimeo-video-thumbnail

February 2024

vimeo-video-thumbnail

December 2023

vimeo-video-thumbnail

November 2023

vimeo-video-thumbnail

October 2023

vimeo-video-thumbnail

September 2023

vimeo-video-thumbnail

August 2023

vimeo-video-thumbnail

July 2023

vimeo-video-thumbnail

June 2023

Play Video

May 2023

Play Video

April 2023

Play Video

January 2023

Play Video

December 2022

Play Video

November 2022

Play Video